Sunday 12 December 2010

Week-14-CRM

12 Dec 2010
Total 6 hours
  1. <Documentation> 6 hours Today I have finished installation manual. And I tried to follow other person's format. But it is difficult and takes long time, because that is original format. Sometimes I have to search what format they use. I want to finish today.
11 Dec 2010
Total 6 hours
  1. <Documentation> 6 hours Still I'm doing installation manual. I took capture everything, so I need to write explanation one by one. I want to finish by tomorrow. And now I'm doing web development job, which is ordered by my friends. I am very busy this week.

10 Dec 2010
Total 6 hours
  1. <Set up server> 6 hours Today I have done only to help set up server. Because my classmates' web site is shown some errors, they were supposed to make presentation again. But they cannot show server, so they used local machine. They will pass, but the fixing problem is required. That's why I helped them. I think my classmates need to get more problem solving skills. The reason of the error is that Master page error, which has left menu contents inside contents place holder. Therefore, IIS is shown error.

8 Dec 2010
Total 6 hours
  1. <Documentation> 6 hours I have finished design documentation. And I got feedback this documentation also. However, still I have to do installation manual. When I set up server, I asked my team member to take capture or not. At that time, we haven't known we need to write installation manual, so I didn't take capture. Now I regret that I didn't take capture, because I set up server 4 times. Now I starts to set up again.

7 Dec 2010
Total 6 hours

  1. <Presentation> 3 hours I joined the presentation. We have already finished our presentation, so we felt relax! However, I helped other team. That's why sometimes I worried their presentation. I think compering this semester with last semester we have done quite well. But this time only one team have passed. Two teams were left. I hope everyone will finish this week.
  2. <Documentation> 2 hours I spend to help setting their server, so I cannot spend the time to write documentation. The documentation takes a lot of time. I want to finish this week.


6 Dec 2010
Total 6 hours


  1. <Server setting> 4 hours I helped other team to upload their application. I have suggested that they have to check before presentation because environment is completely different. However, they were busy for modifying their source code. Anyway, I hope they will pass this week!
  2. <Documentation> 2 hours I have to finish my documentation, but I also help other team. I don't have enough time to do my documentation. Which is the important...?

Thursday 2 December 2010

Week-13-CRM

03 Dec 2010
Total 4 hours

  1. <Presentation> 4 hoursToday, we had final presentation. If we can pass this presentation,  we can graduate this year. If not, we need to continue up to all teachers are agree with the level. So this is the most important time for us. I prepared yesterday without internet connection. This morning, I want to connect to the internet, however we cannot see network card. The reason is network card was burned. Therefore, we changed network card and configure IP address. I used virtual machine, so firstly I cannot connect to the internet, that's why I became nervous. Finally I can connect to the internet, so I feel relief!


02 Dec 2010
Total 8 hours

  1. <Presentation Practice> 4 hours We practiced our presentation, but this time I cannot remember what I want to say. My part is User ID management, schedule, and client details. Topic is not so difficult. However, the logical order is difficult. And sometimes I forgot what I want to explain. Maybe my brain is stopped. I need more practice.
  2. <Upload source code and testing> 4 hours I upload source code to the server. This server normally disconnected from internet. If I want to connect to the internet, I have to ask School staff. Actually, it is not convenient, so source code also need to change depend on the internet connection. I think school must think about the environment. Our teacher said to us that no one have asked about the internet connection. Uhh...n. This is the biggest problem:)
01 Dec 2010
Total 8 hours

  1. <Truncate and create new data> 8 hours Our presentation was postponed, so now we have a time. We decided to truncate database, because some dummy data case trouble. First, truncate our database and then we want to insert front page. So test data should be logical. But it takes long time....

30 Nov 2010
Total 6 hours

  1. <Connect to the internet> 6 hours We were supposed to make a presentation today. And we would like to finish this semester. But we have internet connection problem. Because this server has only one network card, so I set up another network card. However, it was broken, so I cannot connect to the network. I changed to the new network card. It worked, so I feel relief.


29 Nov 2010
Total 10 hours

  1. <Server setting> 10 hours I want to use a physical server not virtual machine. So this morning, I set up everything. However, I know we cannot use this server, so again I need to set up. The reason why I don't use this virtual machine is that windows 2003 server couldn't install SQL 2008 server. After I said to the teacher about the problem, they gave us windows 2008 server. Hardware setting is taking time. I'm really exhausted.